Updates as of July 2013

Furthermore, the site development plan for Phase 3 is now being finalized and will be introduced fourth quarter of this year at the latest.

The burgeoning community within Phase 1 & 2 of the Sunshine Fiesta Project bodes well for additional joint venture projects in the very near future with local and international top land developers.

Updates as of October 2012

House Contruction – As of October 2011, a total of 358 housing units have been constructed from Block 1 – 20 & 27 of Phase 1. Another 100 units shall be built before the year end covering Block 13 – 18.

Meralco Updates – Meralco has completed installation of 73 Meralco poles beginning from the Junction at East National Road going towards new Cardona Diversion Road up to Sunshine Fiesta Spinal Road. The new installation of power lines including transformers with 20kV primary wire, covers the housing units up to Block 17 of Sunshine Fiesta Subdivision.

Water Supply – Water distribution lines fronting the units from Block 1 to a certain Block has been completed. The 3,500 gallon tank ar the open are has been installed. The submersible pump is being installed for the interim supply of the daily water needs of move-in buyers.